McDonalds

Strip out of existing restaurant at ground level and 6 No. apartments on the upper levels. Works were carried out of over 5 floors (including a basement). Contract involved the removal of various existing walls and floors, and reinstating same to form new Mc Donald’ s restaurant lay out. Enabling works played a major roll in the works carried out.

Project Details

Construction Period : Feb – June 2013
Value : €600,000.00
Location : Temple Bar, Dublin 2
Client : McDonalds Ireland
Project Architect : Arthur Gibney & Partners
Project Engineer : Hogan Lynch